Faza Water Supply Project:

Country:

  • Kenya

Clinet:

  • Embassy of Islamic Republic of Iran in Kenya- Lamu County Government

Objective:Conveying 75 CM water per day from mainland to the Faza Island

Status of project:completed in 2014
Location:Faza Island, South east of Kenya in Indian Ocean.
Water resource: Wells in the mainland
Length of pipe line: 14 Km (4 Km in the mainland, 10 Km subsea pipe laying)
Pipe diameters:90 mm
Transmission rate:1.7 lit/sec
Consumption:Faza village drinking water
Pipe material: HDPE
Transmission type: Pumping
Pumping Head: 60 m
No. of pump stations: 2
No. of pumps: 3 units
Electricity demand: 3 generators with the capacity of each 5.5 KVA
Faza Water Supply Project
Faza Water Supply Project
Faza Water Supply Project
Faza Water Supply Project